External Cladding — Bill of Quantities

Project: 31 Rosanna Rd, Heidelberg · Format: Detailed Takeoff · .xlsx
CodeDescriptionQtyUnitNotes / Ref
SECTION AMaterial Cost — Aluminium Panels (Canopies)
1aSolid Aluminium Cladding Panels — 3mm thick, Cassette System, 24mm Top Hat (canopies, flat)87.0030% wastage applied
1bSolid Aluminium Cladding Panels — 3mm thick, Cassette System, 0.15m depth return, 24mm Top Hat2.0630% wastage applied
1cGrand Total Aluminium Panel Supply (incl. 30% wastage)115.78Confirm colour with client
1dIntermediate Top Hat — 24mm, 450mm c/c spacing (subframe for canopy panels)207.81lm5% wastage applied
SECTION BMaterial Cost — Hardies Scyon Axon Cladding
2.1aScyon Axon Cladding — Colour 1, 133mm spacing, 9mm thick, 3.8m height, 24mm Top Hat @ 600mm, 19mm cavity batten, Smooth finish24.91Colour TBC
2.1bScyon Axon Cladding — Colour 1, 133mm spacing, 9mm thick, 7.35m height, 24mm Top Hat @ 600mm, 19mm cavity batten, Smooth finish11.10Colour TBC
2.1cScyon Axon Cladding — Colour 1, 133mm spacing, 9mm thick, general elevations, 24mm Top Hat @ 600mm, 19mm cavity batten, Smooth finish383.34Colour TBC
2.2aScyon Axon Cladding — Colour 2, 133mm spacing, 9mm thick, 3.1m height zone, 24mm Top Hat @ 600mm, 19mm cavity batten, Smooth finish23.28Colour TBC
2.2bScyon Axon Cladding — Colour 2, 133mm spacing, 9mm thick, general elevations, 24mm Top Hat @ 600mm, 19mm cavity batten, Smooth finish74.70Colour TBC
2GTGrand Total Hardie Cladding Supply (incl. 30% wastage)672.53
2THIntermediate Top Hat — 24mm H × 0.75 BMT, 600mm c/c (subframe for Hardie panels)905.33lm5% wastage
2BRBrackets / Clips (Hardie cladding subframe)1,975.35lm
2PKPackers / Shims — bracket spacing 900mm2,194.83nos
SECTION CFixings
3.130mm Series 500 ScrewsnosAllow
3.212 Gauge Hex ScrewsnosAllow
3.3Phillips Stitching ScrewsnosAllow
3.4Flat Phillips Head ScrewsnosAllow
SECTION DSarking / Wrap
4.1Waterproof Sisalation SarkingRollQty to be confirmed
4.2Sisalation Tape / SealantsItemAllow
SECTION E–GLabour, Fabrication & Preliminaries
BLabour CosthrsInsert hours + rate
CFabrication Cost
DAccess Works (scaffold / EWP)weeks
EFloat AllowanceItem
FCaulking / Labourlm
GSpotter Variation AllowanceItem

* Supply rates and amounts are entered by the subcontractor pricing the package. Quantities reflect D&C Estimate takeoff output.

Colour-Coded Plan Markups — Bluebeam

Each markup PDF is colour-coded by trade layer. Download a sample below — the full file is delivered in your inbox immediately after filling your details.

Preview lockedDownload to view full markup
Cladding / Painting

End of Trip Facility

Bendigo Bank, Melbourne · 8 pages · 6 layers

Preview lockedDownload to view full markup
Painting & Finishes

Timbumburi PS Admin

Timbumburi NSW · 14 pages · 6 layers

Preview lockedDownload to view full markup
Resilient Flooring

Ferndale Park Pavilion

Glen Iris VIC 3146 · 12 pages · 8 layers

Preview lockedDownload to view full markup
Roofing / Waterproofing

Ferndale Park Pavilion

Glen Iris VIC 3146 · 10 pages · 5 layers

Preview lockedDownload to view full markup
Painting

543 Hume Drive, Fraser Rise

Fraser Rise VIC 3336 · 17 pages · 4 layers

Preview lockedDownload to view full markup
Masonry

MacKillop College

Melbourne · 29 pages · 7 layers

Want a full package for your specific trade?

We can share a sanitized real takeoff matching your exact trade and project type. Book a 15-minute call or send us a message.